Chicago CH1 Data Center Construction Updates

by NTT Global Data Centers Americas
21 October 2020

Stay up to date on the latest news and milestones from our new Chicago data center campus currently under construction.

October 2020

 

 

August 2020

The construction team has used a crane to lift the chillers to the roof of the building. The chillers are used to circulate cool water throughout the building.

July 2020

Installation on the IT Room is under way. The main distribution frame, connects NTT’s infrastructure in the Chicago data center to the many providers and locations across the globe. The yellow and white track running above the MDF, otherwise known as the cable track, carries the signal from an enclosure to the MDF and out to the world.  

June 2020

CH1 Vault Flooring

The team is preparing to pour the concrete flooring for vault one. This design includes a slab flooring and fan wall cooling technique. 

May 2020

NorthEast Walls

The North East exterior and South West exterior is in progress. Steel and glass will be placed over the wall studs in the next phase of construction. This is the exterior of where the ops team and other offices will be located. The concrete wall to the far right is where the vaults are located.

Partitioned walls

The interior partition framing is in progress. 

The prefabricated exterior walls of the building have been shipped in and installed. By using prefabricated exterior walls we are able to simultaneously build out the interior speeding up timelines of construction. 

 

April 2020

CH1 Roof Installed

The roof has been set, next the precast walls will be shipped to the site and installed to the sides of the building. 

 

March 2020

Setting the Bean

The steel was officially topped out at the NTT CH1 project.  Honoring a long standing tradition, the final steel beam was painted white and affixed with the American flag.  The beam was then signed by the ironworkers and other tradesmen.  They also added the names of project team members from Clune, Verity and Linesight before it was hoisted into place. The topping out ceremony marks a very exciting milestone for this site!

 

November 2020

CH1 Construction has begun

The first 6MW of critical IT load is currently under construction and is available for pre-lease. “The first building on our Chicago Data Center campus is standing up its core and shell now,” said Doug Adams, President and CEO of NTT Global Data Centers Americas (formerly known as RagingWire Data Centers). “By using modular construction techniques, economies of scale, and carefully planned supply chain management, we have lowered construction costs and will be able to affordably offer all the space and critical IT power needed to help companies grow and scale their data center presence as their business needs evolve.”  

 

October 2019

CH1 Exterior

Introducing NTT’s Chicago Data Center campus. The 19-acre campus is located in Itasca, Illinois, which is in the prime area for wholesale data centers. The campus will have two buildings offering a total of 72 megawatts of critical IT load. Each of the two buildings will offer 36 megawatts and 250,000 sq. ft. of space spread over two stories. The first six megawatts of critical IT load will be available in late 2020.

NTT Global Data Centers Americas